Facilities Maintenance

Cadbury Cocoa Plant, Bournville

Bournville entrance
Cadbury factory external

Click to view larger

Client: adi Group
Decoration Dates: September 2015 - November 2015
Overall value: £18k
Labour Resource at Peak: 2

Description:  Decoration works Cocoa Plant rooms and offices, including wall, architraves, skirting and soffitts, columns and beams.

The adi Group manage the planned and reactive technical maintenance for the Cadburys factory in Birmingham.

Our decoration works in this historic building centred on an area that is to be transformed in to a small pilot manufacturing facility. The existing paint coatings had deteriorated due to their age and were completely removed. These coatings were then replaced with specified hygiene coatings, which were water-based and quick drying, which in an area with little natural light or natural ventilation were important factors. Some of the more difficult areas to access were sprayed.