Client: Kier
Decoration Dates: April 2015 - November 2015
Overall value: £100k
Labour Resource at Peak: 10

This £30m project was awarded to Kier under the ProCure 21+framework and brought all emergency services together under one roof. The building works included a new A&E department, offices and wards which were linked to the existing heart and lung building.

Particular care had to be taken with this project as while it was largely a new build, it was on a live hospital site which meant that disruption to patients and hospital staff had to be minimised. The project for us has been straight-forward and smooth, largely due to excellent working relationships with our client and good planning to ensure works were completed on time, on quality and with no accidents.