William Perkin CofE High School

Aerial View
Internal CLT Sports Hall

Click to view larger

Client: Kier
Decoration Dates: Jan 13 - Sept 13
Overall value: £180k
Labour Resource at Peak: 25

William Perkin High is the latest in a succession of challenging, high-speed school projects Kier has undertaken using CLT.

The new school has places for 1,200 11 to 16-year-olds, plus a sixth form with places for 250 students and a centre for children with special educational needs. The local community will also be able to use the school’s facilities, which include five sports pitches, floodlit hard playing surfaces, indoor sports hall and activity studio.

Works were succesfully completed for the first handover in August 2013, and practical completion achieved in October 13 easily intime for the planned April 14 intake.